Mercer Corridor Project (East Phase)
Weekly Construction Preview

mercer_logo_200This week, crews will continue to focus on underground utility work on Valley Street and Broad Street and expand construction activities on Westlake Avenue N north of Mercer Street.

Activities this week include:

  • Continue Westlake Avenue N underground utility installations including storm drainage and sewer work north of Mercer Street.
  • Continue Seattle City Light and communications duct bank work on Valley Street between Terry Avenue N and Westlake Avenue N.
  • Continue landscaping installation on Fairview Avenue N between Valley Street and Mercer Street and on the south side of the I-5 on-ramps at Mercer Street.

Traffic engineers will continue to:

  • Monitor traffic flow on Mercer Street and newly re-opened Fairview Ave. N.
  •  Monitor traffic on 9th Avenue N.
  • Monitor traffic flow at the Dexter Avenue N and Mercer Street intersection.

For up-to-minute construction updates join our project email list at: http://www.seattle.gov/transportation/mercercorridor.htm  or call the 24-hour construction hotline at 206-419-5818.