Construction work on the South Park Bridge site has shifted a little. As King County DOT explains, “crews are demolishing the old bascule pier, working until 7 pm each night in order to meet the project schedule.”
Formwork is being installed on the new piers by both day and night crews, as the old bascule pier comes down. Since this is relatively quiet work, crews will be up working until about 1 a.m. and you can expect to see this kind of work for about five more weeks.
Check out the bridge construction in progress with the South Park Bridge Cameras: http://www.kingcounty.gov/transportation/SouthParkBridge/BridgeCameras.aspx
For more information about the South Park Bridge Replacement Project, visit King County Department of Transportation’s website at http://www.kingcounty.gov/transportation/SouthParkBridge.aspx