When the Virginia Street paving project wraps up it will mark the completion of paving in the north end of Downtown that has been ongoing on 2nd, 4th, 5th, Stewart, Olive, Pike and 3rd for the better part of three years! After seven months, the last segment of the Virginia paving project is nearing completion, with the very last weekend closure taking place last weekend on Virginia between 2nd and 3rd avenues (to place concrete pavement in the bus lanes). This week has focused on asphalt grinding, and final paving is tentatively scheduled for August 10th and 11th. After that it’s just striping and touch ups…ah, the memories…
The North Downtown Paving Pinnacle
by July 29, 2010
on