Find Posts By Topic

Mercer Corridor Project (East Phase) – Weekly Construction Update

Vault installation on Saturday.

This week, crews are focusing on pavement removal and grading on the west side of Fairview Avenue N between Mercer Street and Harrison Street and installation of new signal poles and mast arms at the intersection of Fairview Avenue N and Mercer Street.

Activities this week include:

  • Begin pavement removal and grading on west side of Fairview Avenue N between Mercer Street and Harrison Street in preparation for rebuilding the roadway.
  • Begin underground water main work on Valley Street and Terry Avenue N.   Work occurs nightly from 7:00 p.m. to 5:00 a.m. through December 20.  Traffic impacts will include:
    • Westbound Valley Street is  restricted to one lane between Boren Avenue N and Westlake Avenue N while crews work in the center lane.
    • Terry Avenue N is restricted to southbound traffic only between Valley Street and Mercer Street while crews work on the east side of the roadway.
    • Flaggers are positioned to maintain traffic flow and assist vehicles and equipment entering and exiting the work zone.
  • Continue signal pole and mast arm installation at the intersection of Fairview Avenue N and Mercer Street.  Please note this work will require two lanes of eastbound Mercer Street to be restricted between Terry Avenue N and Fairview Avenue N for approximately two weeks. 
    • Work occurs on weekdays during non-peak traffic hours from 9:00 a.m. to 3:00 p.m.
    • Vehicles are being routed around the work zone and a uniformed police officer will be positioned to facilitate traffic flow.
  • Continue concrete installation on Fairview Avenue N between Mercer Street and Valley Street.
  • Continue Seattle City Light duct bank work and catch basin installation on the west side of Fairview Avenue N between Mercer and Harrison streets in preparation for rebuilding sections of the roadway.
  • Continue work on the median and cast in place wall for the I-5 on- and off-ramps at Mercer Street. Please note this work will be located out of traffic and will not require lane restrictions on the I-5 on- and off-ramps at Mercer Street.
  • Continue pole foundation and conduit installation on Fairview Avenue N.

Traffic engineers adjusted the signal timing along the Mercer Corridor for the off-peak and weekend hours.  They will continue to:                                   

  • Monitor traffic flow on Mercer Street.
  • Monitor traffic flow at the Dexter Avenue N and Mercer Street intersection.

As always, for up-to-minute construction updates join our project email list at: www.seattle.gov/transportation/ppmp_mercer.htm or call the 24-hour construction hotline at 206-419-5818.