This week, crews will focus on pavement removal and grading on the west side of Fairview Avenue N between Mercer Street and Harrison Street and continuing utility installations on Fairview Avenue N between Mercer Street and Valley Street.
Activities this week include:
- Begin concrete pavement on west side of Fairview Avenue N between Mercer Street and Harrison Street. Please note, this work is weather dependant.
- Continue pavement removal and grading on west side of Fairview Avenue N between Mercer Street and Harrison Street in preparation for rebuilding the roadway.
- Continue catch basin installation on the west side of Fairview Avenue N between Mercer and Harrison streets and on Roy Street in preparation for rebuilding sections of the roadway.
- Continue pole foundation and conduit installation on Fairview Avenue N.
- Continue Seattle City Light duck bank work on Fairview Avenue N between Mercer Street and Valley Street.
Traffic engineers will continue to:
- Monitor traffic flow on Mercer Street.
- Monitor traffic flow at the Dexter Avenue N and Mercer Street intersection.
For up-to-minute construction updates join our project email list at: www.seattle.gov/transportation/ppmp_mercer.htm or call the 24-hour construction hotline at 206-419-5818.