This week, crews continued to focus on pavement removal and grading on the west side of Fairview Avenue N between Mercer Street and Harrison Street and signal pole and mast arm installation on eastbound Mercer Street.

Activities this week included:

  • Continued underground water main work on Valley Street and Terry Avenue N.
  • Continued signal pole and mast arm installation at the intersection of Fairview Avenue N and Mercer Street.
  • Began pavement removal between Valley Street and Mercer Street and continued pavement removal and grading on west side of Fairview Avenue N between Mercer Street and Harrison Street and in preparation for rebuilding the roadway.
  • Began installing concrete pavement on west side of Fairview Avenue N between Mercer Street and Harrison Street.
  • Continued catch basin installation on Roy Street in preparation for rebuilding sections of the roadway.
  • Continued Seattle City Light duck bank work on Fairview Avenue N between Mercer Street and Valley Street.

Traffic engineers will continue to:

  • Monitor traffic flow on Mercer Street.