Crews are working on underground utilities on Valley Street.

Crews are working on underground utilities on Valley Street.



mercer_logo_200

This week, crews continued to focus on underground utility work on Valley Street and Broad Street.Activities this week included:

  • Continued electrical vault installation on Broad Street between 9th Avenue N and Westlake Avenue N.
  • Continued landscaping installation on Fairview Avenue N between Valley Street and Mercer Street.
  • Continued Seattle City Light and communications duct bank work on Valley Street.
  • Completed the cast in place wall installation on the north side of the I-5 off-ramps.
  • Began working on the landscaping installation on the south side of the I-5 ramps.

Traffic engineers will continue to:

  • Monitor traffic flow on Mercer Street and newly re-opened Fairview Avenue N.
  • Monitor traffic flow at the Dexter Avenue N and Mercer Street intersection.

For up-to-minute construction updates join our project email list at: http://www.seattle.gov/transportation/mercercorridor.htm  or call the 24-hour construction hotline at 206-419-5818.