mercer_logo_200This week, crews will begin construction on the north side of Mercer Street between Fifth Avenue N and Dexter Avenue N and the east side of SR 99 between Valley Street and Harrison Street. They will also continue to work on underground utilities on Valley Street, Broad Street and Westlake Avenue N north of Mercer Street.

 Activities this week include:

  • Begin sidewalk and pavement removal on the north side of Mercer Street between Fifth Avenue N and Dexter Avenue N and on the east side of SR 99 between Valley and Harrison streets.
  • Begin sidewalk removal on the north side of Roy Street between Queen Anne Avenue N and First Avenue N in preparation for signal improvements at both intersections. Please note, the north sidewalk on Roy Street and adjacent parking lane will be closed for approximately two weeks.
  • Continue Seattle City Light and communications duct bank work on Valley Street between Terry Avenue N and Westlake Avenue N.
  • Continue landscaping installation on Fairview Avenue N between Valley Street and Mercer Street and on the south side of the I-5 on-ramps at Mercer Street.

Reminder: Mercer Street between Fifth Avenue N and Ninth Avenue N is now restricted to two eastbound lanes following a full weekend closure of Mercer Street and SR 99 and Broad Street is now open for eastbound and westbound traffic. For more information on associated traffic impacts, please visit our website at: http://www.seattle.gov/transportation/mercercorridor.htm

Traffic engineers will continue to:

  • Monitor traffic on Mercer Street, Fifth Avenue N, Broad Street and Ninth Avenue N.
  • Monitor traffic at the Westlake Avenue N and Mercer Street intersection.
  • Monitor traffic flow at the Dexter Avenue N and Mercer Street intersection.