Mercer Corridor Project
Weekly Construction Preview

mercer_logo_275This week, crews will continue sidewalk and landscaping work on Valley Street between Fairview Avenue North and Ninth Avenue North. Construction will also continue on Mercer Street between Fifth Avenue North and Dexter Avenue North and the east side of SR 99 between Valley and Harrison streets.

Activities this week include:

  • Began intermittent single lane closures on the I-5 on-ramps at Mercer Street on October 28 and 29 to accommodate landscaping.
    • Work will occur on the north side of the I-5 on-ramp with the far left lane on eastbound Mercer Street closed between Boren Avenue North and onto the I-5 on-ramps at Mercer Street. Two lanes onto the I-5 on-ramps will remain open at all times.
    • Continue sidewalk restoration on Valley Street between Ninth Avenue North and Fairview Avenue North.
  • Continue landscaping and paver installation on Westlake Avenue North and Valley Street.
  • Continue sidewalk work and conduit installation on the north side of Mercer Street between Queen Anne Avenue North and Fourth Avenue North.
  • Continue sidewalk improvements on Roy Street at Fifth Avenue North.
  • Continue installing concrete panels on the north retaining wall on Mercer Street between Fifth Avenue North and Dexter Avenue North.
  • Continue installing utilities on the south side of Mercer Street between Fifth Avenue North and Aurora Avenue North.
  • Continue work on the north and south ends of the east side of the SR 99 bridge.
  • Continue electrical work along the south side of Mercer Street between Eighth Avenue North and Dexter Avenue North.