Westlake Cycle Track is Nearly Halfway Done

SDOT’s Westlake Cycle Track Project is reaching the halfway point! The protected bike lane along Westlake Avenue North will provide a safer place for people riding bikes, walking and driving, while improving connectivity and accessibility for all travelers in the Westlake area.

Construction recap – from January to May

Westlake before cycle track construction

An early photo of the Westlake corridor before construction began in January.

Construction of the protected bike lane began in January this year and is separated into four phases. Phase 1 and Phase 2 are on the north end of the corridor and are nearly complete.

Westlake completed section

Completed section of the protected bike lane in Phase 1 in the north end of the corridor.

Our construction team is coordinating with Westlake businesses and residents to minimize construction impacts as they work to finish the project as safely and efficiently as possible.

Westlake work near Railroad Park

Work on the protected bike lane continues near Railroad Park in Phase 2.

Our crews are making progress on Phase 3 in the south end.

Westlake Phase 3

Forming for the protected bike lane in Phase 3 in the south end of the corridor.

This Friday, May 6, from 7 – 9 a.m., keep an eye out for volunteers from Cascade Bicycle Club and the outreach team on the north end of the corridor. We’ll help guide people riding bikes to enter the first half of the protected bike lane. We will also be promoting safety education for all users.

The Westlake Cycle Track is scheduled to be complete in summer 2016, so get those bikes ready and sign up for email updates to stay up-to-date on construction progress!