This week, crews will continue to focus on concrete pavement on the west side of Fairview Avenue N between Mercer Street and Harrison Street and underground electrical work at Fairview Avenue N and Valley Street.

Activities this week include:

  • Begin sewer work and tie-in at Boren Avenue N and Valley Street.
  • Continue pavement removal and grading on Fairview Avenue N between Valley Street and Mercer Street in preparation for rebuilding the roadway.
  • Continue concrete pavement installation on west side of Fairview Avenue N between Mercer Street and Harrison Street.
  • Continue Seattle City Light electrical duck bank work on Fairview Avenue N between Mercer Street and Valley Street.
  • Continue pole foundation installation for future street lights on west sides of Fairview Avenue N between Mercer Street and Harrison Street.

 Traffic engineers will continue to:

  • Monitor traffic flow on Mercer Street.
  • Monitor traffic flow at the Dexter Avenue N and Mercer Street intersection.