Mercer Corridor Project (East Phase)
Weekly Construction Preview

This week, crews are focusing on concrete pavement installation on Fairview Avenue N between Valley Street and Mercer Street and sidewalk restoration on Fairview Avenue N between Harrison Street and Mercer Street.

Activities this week include:

  • Continue signal installation at Republican Street and Fairview Avenue N.
  • Continue concrete pavement installation on Fairview Avenue N between Valley Street and Mercer Street in preparation for rebuilding the roadway.
  • Sidewalk installation on Fairview north of Valley and also on Roy Street.
  • Continue Seattle City Light duct bank work on Valley Street.
  • Continue conduit and handhole installation for future street lights on west sides of Fairview Avenue N between Mercer Street and Harrison Street.
  • Continue cast in place wall installation on the north side of the I-5 off-ramps.

Traffic engineers continue to:

  • Monitor traffic flow on Mercer Street.
  • Monitor traffic flow at the Dexter Avenue N and Mercer Street intersection.
  • Prepare for the full opening of Fairview Avenue N.

For up-to-minute construction updates join our project email list at: www.seattle.gov/transportation/ppmp_mercer.htm or call the 24-hour construction hotline at 206-419-5818.