Summer is here and SDOT crews are busy

 

N/NE Northgate Way and N 105th project is on target to wrap up this summer.

N/NE Northgate Way and N 105th project is on target to wrap up this summer.

 

The Seattle Department of Transportation (SDOT) is on track to meet its 2014 goals for the Bridging the Gap (BTG) transportation initiative. As summer begins, we have moved into the busy construction season and you can find work on BTG projects all across the city. SDOT has been busy paving roads, constructing new sidewalk, installing new signs and restriping roadway markings. BTG continues to make steady progress towards its nine-year goals.

This year, SDOT will complete two major paving projects – N 105th, N/NE Northgate Way and Holman Road – both projects are underway and will bring 17 new lane-miles of paving. And that’s not all, since January:

  • 15 new crossing improvements have been implemented and new pedestrian countdown signals installed at 40 intersections.
  • 263 new bicycle parking spaces and 14 miles of bike route signs have been installed. Crews have also inspected 40 miles of trails.
  • Three Safe Routes to School projects have been completed, 56 new curb ramps have been constructed and 11 school zones have been improved.
  • 444 new street trees have been planted so far this year and more than 457 have been pruned.

SDOT crews are also chipping away on much-needed maintenance work as well. Just this year, they have already replaced more than 1,558 regulatory traffic signs, installed new street name signs at 487 intersections, remarked more than 240 crosswalks and replaced 796 linear feet of poor guard rail.

During the seven and half years of the levy, the City has delivered on the promises made by Bridging the Gap. To date SDOT has paved 205 lane-miles of road, secured 50,000 new hours of transit service, constructed 100 blocks of new sidewalk, repaired 167 blocks of sidewalk, remarked 4,729 crosswalks, replaced 44,439 regulatory signs, installed school zone signage at 196 schools, replaced street name signs at 9,873 intersections, striped 150 miles of bike lanes and sharrows and planted 5,569 new street trees.

For more information about BTG and its goals and progress towards meeting those goals, please visit the BTG web page.