Find Posts By Topic

New Curb Ramps at 15th Avenue NE and NE Brockman Place

The Seattle Times submitted a number of reader questions about transportation related work around the city.  Reader comment:  “The city very diligently put in wheelchair access curbs and then did nothing to make the rest of the sidewalks accessible.” As part of a roadway repaving program, curb ramps are typically… [ Keep reading ]

New Sidewalk at 30th Avenue S, South of Jackson Street

The Seattle Times submitted a number of reader questions about transportation related work around the city.  Reader comment:  “Work done and redone several times.”  Pouring of concrete in this location was deliberately done in phases over several days, not because of rework.  There was one instance during this project where… [ Keep reading ]

Concrete Work around Utility Cover at Meridian Avenue N and N 34th Street

The Seattle Times submitted a number of reader questions about transportation related work around the city.  Reader comment:  “A manhole cover that partially blocked the intersection for close to a week while it dried, only to become very cracked within weeks of job completion.” This work was completed seven years… [ Keep reading ]

Ramp at 95th and 20th NE, and New Sidewalk without Curb Ramp at 98th and 20th NE

The Seattle Times submitted a number of reader questions about transportation related work around the city.  Reader comment:  “One ends with a steep path into the park.  At 98th and 20th NE, workers removed the wheelchair ramp and replaced it with a sidewalk that has no wheelchair ramp.” SDOT performed… [ Keep reading ]

Concrete Work at Cascade Park, Corner of Harrison and Minor Streets

The Seattle Times submitted a number of reader questions about transportation related work around the city.  Reader comment:  “Was poured and repoured seven or eight times.” This project was a collaboration of multiple agencies, including SDOT.  The project was phased and planned for each agency to perform their requirements without… [ Keep reading ]

Curb Ramp Markings at 24th Avenue E and Boyer Avenue

The Seattle Times submitted a number of reader questions about transportation related work around the city.  Reader comment:  “For weeks the crew was replacing the sidewalk and street.  Now all four corners are marked for ramp access.” The markings for the curb ramps were placed there to ensure that the… [ Keep reading ]

New Sidewalk at 8740 Phinney North

The Seattle Times submitted a number of reader questions about transportation related work around the city.  Reader comment:  “Edge of the sidewalk was not at the same level as the street and the sidewalk was torn up and redone.” This is an example of rework by a private contractor.  SDOT Street… [ Keep reading ]

New Sidewalk at 90th and Phinney Ave N

The Seattle Times submitted a number of reader questions about transportation related work around the city.  Reader comment:  “Poured an enlarged wheelchair ramp and then tore it (out) shortly afterward.” This was a sidewalk project where the sidewalk went around a corner on a slope.  SDOT crews properly followed the… [ Keep reading ]

Walkers of the world, unite!

It’s going to be a week of pedestrian news for the blog, starting today with a new strategy to keep peds moving next to SDOT’s Second Avenue downtown paving project. Quick background: SDOT is involved in the walk through and next to construction zones in two ways.  First, we coordinate… [ Keep reading ]

SDOT Simple Solutions

If you watched the local news last night, you probably heard the stories about the University Bridge closure due to the extreme temperatures.   Anticipating that the bridges would expand in the record-breaking heat, our SDOT bridge engineers had been carefully monitoring Seattle’s bridges all week.  All our other moveable bridges… [ Keep reading ]