Weekly Update: West Seattle High-Rise Bridge Stabilization

Every Monday, we’re posting a blog to keep you informed about our progress to stabilize the bridge, our efforts to address traffic and mobility, and other items related to the West Seattle High-Rise Bridge closure. In this week’s update: West Seattle High-Rise Bridge stabilization update West Seattle Bridge Community Task… [ Keep reading ]

The West Seattle Bridge Community Task Force has met twice recently – once with Mayor Durkan – as we get closer to a decision to repair or replace the bridge.

Watch the 10th West Seattle Bridge Community Task Force Meeting on YouTube. (This week’s meeting will be available soon!) Summary At our 10th West Seattle Bridge Community Task Force meeting last week, Mayor Durkan continued to express how important it is for her to prioritize equity, protect lives and preserve public safety. During the Q&A… [ Keep reading ]

Weekly Update: West Seattle High-Rise Bridge Stabilization

Every Monday, we’re posting a blog to keep you informed about our progress to stabilize the bridge, our efforts to address traffic and mobility, and other items related to the West Seattle High-Rise Bridge closure. In this week’s update: High-Rise Bridge Stabilization Update Paving at West Marginal Way SW and… [ Keep reading ]

Weekly Update: West Seattle High-Rise Bridge Stabilization

Every Monday, we’re posting a blog to keep you informed about our progress to stabilize the bridge, our efforts to address traffic and mobility, and other items related to the West Seattle High-Rise Bridge closure. In this week’s update: High-Rise Bridge Stabilization Update Progress on projects over the weekend This… [ Keep reading ]

Weekly Update: West Seattle High-Rise Bridge Stabilization

Last week, we shared our first weekly update about the work we’re doing on the West Seattle High-Rise Bridge. You can expect an update every week. Our goal is to keep you informed of our sustained progress to stabilize the bridge, efforts to address traffic, and other updates related to the… [ Keep reading ]

Weekly Update: West Seattle High-Rise Bridge Stabilization

Since the closure of the High-Rise Bridge, we’ve worked to simultaneously advance all efforts needed to expeditiously pursue both a repair or replace scenario. By advancing both pathways at once, not a moment has been lost while the careful and thorough assessment is done to understand which avenue – repair or replace –… [ Keep reading ]

Since March, we’ve implemented 175 changes to support communities affected by the West Seattle Bridge closure

During the closure, we’re working to keep people moving, lessen the impacts to the best of our ability, and preserve/enhance public safety. We know that no level of traffic mitigation can overcome the 100,000+ travelers displaced across West Seattle, Duwamish Valley, and Seattle as a whole by the closure of the… [ Keep reading ]

Mayor Durkan and West Seattle Bridge Community Task Force addressed individual, community, small business, and industry needs alongside environmental justice in August 19 meeting

The West Seattle Bridge Community Task Force is one of the many ways that we ensure the communities’ voices are at the center of our West Seattle Bridge decisions. Community Task Force members represent neighborhoods, industries, government, and services across West Seattle and nearby communities. In the latest Community Task Force meeting on August 19,… [ Keep reading ]

SDOT selects HNTB to design the West Seattle Bridge replacement, a necessary step for all repair or replacement scenarios.

Today, we’re excited to announce that we’ve reached a major milestone in our work to restore mobility to West Seattle, the Duwamish Valley, and other communities impacted by the West Seattle High-Rise Bridge closure. Through the Request for Qualifications process, we’ve selected the infrastructure solutions firm HNTB Corporation to design the West Seattle Bridge replacement. This work will be needed… [ Keep reading ]

SDOT seeks City interfund loan to cover 2020 and Q1 2021 expenses, sets up new Capital Improvement Program for West Seattle Bridge Program.

2020 has been a year brimming with unanticipated, unprecedented, and consequently, unbudgeted challenges. The rapid growth of cracks in the West Seattle High-Rise Bridge observed in late March, leading us to immediately remove all traffic, has been no exception. As public safety is our number one priority, we immediately jumped into action to slow cracking, determine the structural state of the bridge, and to… [ Keep reading ]