Posts tagged with quarterly report Archives - SDOT Blog

Check out our latest quarterly report for Reconnect West Seattle – Quarter 2, 2022

We have completed 59 of the 70 Reconnect West Seattle Implementation Plan projects from 2020-2022. We have completed 51 of the 64 Home Zone project elements. And we have completed 275 traffic mitigation projects since March 2020. Overview Reconnect West Seattle was developed in response to the unexpected closure of… [ Keep reading ]

Check out our latest quarterly report for Reconnect West Seattle

Overview Reconnect West Seattle was borne out of the unexpected closure of the West Seattle High-Rise Bridge in March of 2020, which dramatically impacted West Seattle and nearby Duwamish Valley communities. Through Reconnect West Seattle, we have a vision to restore travel across the Duwamish to similar levels seen before… [ Keep reading ]

Latest Reconnect West Seattle quarterly report now available (October-December 2021) – Learn about our work to promote safety and mobility in West Seattle and Duwamish Valley communities

Reconnect West Seattle was borne out of the unexpected closure of the West Seattle Bridge in March 2020, which affected West Seattle and the nearby Duwamish Valley communities in a variety of ways. Through Reconnect West Seattle, we are implementing a vision to restore travel across the Duwamish to similar… [ Keep reading ]