Check out our final quarterly report for Reconnect West Seattle – Quarter 4, 2022

Blog stats: 700 words | 4-minute read Since March 2020, we have completed 63 of the 70 projects identified in the Reconnect West Seattle Implementation Plan. We have completed 56 of the 64 Home Zone project elements in South Park, Highland Park, and Georgetown. And we have completed 319 traffic… [ Keep reading ]

Check out our latest quarterly report for Reconnect West Seattle – Quarter 3, 2022

We are excited the West Seattle Bridge has reopened for everyone who lives, works, and visits West Seattle. During the closure, we completed more than 300 traffic mitigation projects to reduce the effects of detour traffic in South Park, Georgetown, Highland Park, and throughout West Seattle. To date, we have… [ Keep reading ]

Check out our latest quarterly report for Reconnect West Seattle – Quarter 2, 2022

We have completed 59 of the 70 Reconnect West Seattle Implementation Plan projects from 2020-2022. We have completed 51 of the 64 Home Zone project elements. And we have completed 275 traffic mitigation projects since March 2020. Overview Reconnect West Seattle was developed in response to the unexpected closure of… [ Keep reading ]

Check out our latest quarterly report for Reconnect West Seattle

Overview Reconnect West Seattle was borne out of the unexpected closure of the West Seattle High-Rise Bridge in March of 2020, which dramatically impacted West Seattle and nearby Duwamish Valley communities. Through Reconnect West Seattle, we have a vision to restore travel across the Duwamish to similar levels seen before… [ Keep reading ]

Latest Reconnect West Seattle quarterly report now available (October-December 2021) – Learn about our work to promote safety and mobility in West Seattle and Duwamish Valley communities

Reconnect West Seattle was borne out of the unexpected closure of the West Seattle Bridge in March 2020, which affected West Seattle and the nearby Duwamish Valley communities in a variety of ways. Through Reconnect West Seattle, we are implementing a vision to restore travel across the Duwamish to similar… [ Keep reading ]

Our Quarterly Update on Reconnect West Seattle

Reconnect West Seattle was borne out of the unexpected closure of the West Seattle Bridge, which affected West Seattle and the nearby Duwamish Valley communities in many, varied ways. Through Reconnect West Seattle, we have a vision to restore travel across the Duwamish to similar levels seen before the bridge closure and, at the same time, reduce the… [ Keep reading ]

Sal the Salmon explores the trees of West Seattle!

This blog was written by Sal the SpokesSalmon (with the help from her human friends at SDOT). Why, HELLO! It’s ME, Sal, SDOT’s SpokesSalmon who’s getting the word out to #FlipYourTrip and quit driving alone so much. SDOT lets me take over the blog and social media accounts from time… [ Keep reading ]

Thank you for joining us at our West Seattle Bridge virtual public meeting!

Thanks to everyone who joined us for the West Seattle Bridge Program virtual public meeting yesterday! We appreciate those who joined us online to hear updates about the ongoing repair effort on the West Seattle High-Rise Bridge (high bridge), expanded access on the Spokane St Swing Bridge (low bridge), and our work to improve access to and around West Seattle through the Reconnect… [ Keep reading ]

60 new speed humps installed to increase safety in neighborhoods along West Seattle Bridge detour

Join us tomorrow, July 21, at 5:30 PM for a virtual public meeting to discuss bridge repair, low bridge access, and travel options around West Seattle and the Duwamish Valley. You can find more information here. We installed 60 new speed humps in Highland Park, Georgetown, and South Park to increase… [ Keep reading ]

Travel Advisory | Changes coming to West Marginal Way SW and Highland Park Way SW intersection

Starting this weekend, people traveling through the intersection of West Marginal Way SW and Highland Park Way SW will see us working on improvements to make the intersection more accessible, efficient, and safe. Our crews will start the work this weekend and continue for the next several weekends until the work is done. At this intersection, we will: Remove existing raised traffic islands to create a new northbound… [ Keep reading ]